A long-awaited transport project is taking shape, with 45 properties acquired to make way for a four-lane corridor.
For more than two decades, plans to transform one of Maroochydore’s key transport corridors have largely existed on paper.
Now, the first major signs of change are becoming impossible to miss.
Homes and commercial buildings are being demolished along Maud Street as Sunshine Coast Council begins the Sugar Road and Maud Street Transport Corridor Upgrade.
The council has acquired 45 properties across 35 lots on the western side of Maud Street between Bungama Street and Dalton Drive, securing all the land required for that section of the project.
What is happening? – The project will eventually widen Sugar Road and Maud Street from two lanes to four between Bungama Street and Wises Road, providing two lanes in each direction.
The upgrade will also introduce separated walking and cycling paths, signalised and raised priority crossings, new landscaping and shaded pathways.
A Sunshine Coast Council spokesperson says detailed design is underway and expected to be completed by mid-2027.
“Major works on Maud Street are expected to commence when the design is complete, but the project’s full timeline and construction of all stages are subject to future council budget deliberations,” council says.
Why is the road being upgraded? – Sugar Road and Maud Street form one of the main approaches into central Maroochydore from the south, connecting surrounding residential areas with businesses, services and the developing city centre.
The project will also support development around the Maroochydore City Centre Priority Development Area, where new commercial, residential and community facilities are reshaping the region’s urban centre.
The council says the upgrade is intended to accommodate increasing traffic volumes while discouraging motorists from using nearby residential streets as shortcuts.
Improving safety for pedestrians and cyclists is another priority, with dedicated pathways and new crossings designed to reduce conflicts between different road users.
Although demolition is underway, the project has been planned for more than 20 years.
The council has been liaising with affected property owners since 2014 and began progressively purchasing land in 2016. A draft concept design was released for community feedback in 2023.
At the time, divisional councillor Joe Natoli said more than 80 per cent of survey respondents had indicated support for an upgrade.
“The community’s ideas and inputs from community consultation informed further investigations by council, resulting in an updated concept design,” he said.
a new road ahead – For Carole and David Fuller, the road upgrade has meant saying goodbye to a place filled with more than five decades of memories.
The couple purchased their home at 113 Maud Street in 1972, raising their children there and expecting to remain in the property for the rest of their lives.
But after 53 years, their home was acquired to make way for a left-turn lane from Maud Street into Trinder Avenue.
A council spokesperson previously told Sunshine Coast News the property was acquired “through agreement with the owners”.
“In determining purchase prices, council relies on the guidance of a professionally qualified independent valuer to ensure the offer reflects fair market value,” the spokesperson said.
The Fullers subsequently moved into a townhouse complex on Bradman Avenue.
Despite their experience, the couple emphasised they were not opposed to progress.
“The one constant was our home that we intended to stay in until it was on to the next life,” Carole says.
“We understand we are luckier than many. We have a roof over our head, our health and each other.”
Demolition underway – Local construction company Evans Built has been appointed to undertake the removal works.
“Demolition works will continue to be phased over the next six months, to reduce impacts to our community,” a council spokesperson says.
During demolition, two-way traffic will remain available along Maud Street, although temporary traffic control measures and pedestrian diversions may be necessary.
What about Sugar Road? – While all required land has now been secured on the western side of Maud Street, planning for the Sugar Road section remains less advanced.
The number of properties potentially affected along Sugar Road has not yet been confirmed.
When will it be finished? – Despite the progress along Maud Street, there is no confirmed completion date for the entire corridor upgrade.
For more information visit shorturl.at/BGOXY or email sugarmaudupgrade@sunshinecoast.qld.gov.au
THE PROJECT AT A GLANCE
The upgrade: widening Sugar Road and Maud Street from two lanes to four between Bungama Street and Wises Road.
Properties acquired: 45 properties across 35 lots on the western side of Maud Street.
Demolition: began in mid-September this year and is expected to continue in stages for about six months.
Detailed design: expected to be completed by mid-2027.
Major construction: expected to begin on Maud Street after detailed design, subject to council budget decisions.
Sugar Road: further planning and investigations are underway to determine future property acquisitions.